Warrego Gold Plant Complete plant refurbishment Warrego NT 2003 Mintrex
Equigold Sag Mill Upgrade Upgrade 11kV high voltage LRS and motor starter to Sag Mill Mt Rawdon, Qld 2004 Equigold
Cadjebut Lead/Zinc Mine Mine decommissioning & recovery of electrical equipment, power line and power station   2004 Pilbara Mines
Woodie Woodie Manganese Mine 160t crusher and screening plant HV, LV electrical and instrumentation Woodie Woodie, WA 2005 BEC Engineering
Woodie Woodie Manganese Mine 3.7mW power station, power line upgrade including transformer sub-stations Woodie Woodie, WA 2005 BEC Engineering
Kimberley Diamonds 11kV power line and transformer upgrade Derby, WA 2005 Power West
Transalta Agnew Power Station, Emu Feeder HV Cable upgrade Leinster, WA 2006 BEC Engineering
Barrick Gold Corporation Ball Mill Upgrade Upgrade 6.6kV high voltage LRS Ball Mill North Mara, Tanzania 2006 Barrick Gold Corporation
Avoca Gold Mine Heavy Machinery workshop and administration offices, water treatment plant system and infrastructure Norseman, WA 2007 Avoca Resources
Avoca Gold Mine 160 man Camp Power and communication including temporary 48 man camp Norseman, WA 2007-2008 Avoca Resources
Coobina Chromite Mine Electrical, instrumentation and communication installation and commissioning Newman WA 2008 DRA Pacific 
Co-Operative Bulk Handling CLS installation and upgrade Geraldton, WA 2008 Co-Operative Bulk Handling
Cocos (Keeling) Island Fuel Farm Rumah Buru port fuel farm Cocos (Keeling) Island  2009 Springfield Construction
Geraldton Port Authority Upgrade CV502 Upgrade Geraldton WA 2009 Geraldton Port Authority
ADSCS Power Upgrade Bus Duct under floor installation Geraldton WA 2009 Boeing Australia
Pabdury Exploration Camp  Design & Construct 20 Person Accom Camp Meekatharra WA 2009 Precision Camps & Mining
Deepdale Stage 8 Residential Sub Division Geraldton WA 2010 Central Earthmoving
Karara Mining Limited Camp 1600 Person Accommodation Camp Morawa WA 2010-2011 Doric Construction
Karara Mining Limited Main Site Office     Karara Mining Limited
Karara Mining Limited KML Site Infrastructure Works Morawa WA 2010-2013 Karara Mining Limited
Mac Donald Dowel Camp SKA Design & Construct 40 Person Accom Camp Murchison WA 2011 Precision Camps & Mining
FMG Solomon Hub Camp Design & Construct 250 Person Accom Camp Pilbara WA 2011 Precision Camps & Mining
Bluebird Gold Mine Supply and install Bluebird Crusher Panel Meekatharra WA 2012 Geraldton Hydraulics
Wodgina Mine Site Power Upgrade Powerline re-alignment and HV Upgrade Pilbara WA 2011-2012 BEC Engineering
Atlas Iron McPhee Creek Camp Design & Construct 100 Person Accomadation Camp Pilbara WA 2011-2012 Precision Camps & Mining
Burnakura Gold Mine  Kentor Gold Mill & Crushing Circuit Upgrade, 11kV Underground TX Upgrade, Camp Upgrade. Meekatharra WA 2011-2012 Elinco Engineering
Atlas Iron Wodgina Camp Design & Construct 100 Person Accom Camp & Laboratory. Pilbara WA 2012 Precision Camps & Mining
Sodexo Three Springs Camp Power Station Upgrade Three Springs WA 2012 Karara Mining Limited
Karara Mining Limited Main Warehouse, Electrical Workshop, Boilermaker Workshop & Washdown Bay Facilities Morawa WA 2012-2013 VDM Construction
Karara Mining Limited Karara Facility and Analytical Labaratory  Morawa WA 2012-2013 VDM Construction
Bis Industries Bis Workshop and Site Infrastucture, Karara Mine Site Morawa WA 2012-2013 Bis Industries
FL Smidth Mobile Stacker Plant, Karara Mine Site Morawa WA 2012-2013 FL Smidth
Karara Mining Limited RMS 4 x 110kW Mill Discharge Pumps Morawa WA 2013 Karara Mining Limited
White Road, Morawa  Residential Sub Division Morawa WA 2013 Central Earthmoving
Geraldton Heights Stage 1 Residential Sub Division Geraldton WA 2013 WBHO
Technology Park  Commercial Sub Division Geraldton WA 2013 WBHO
Co Operative Bulk Handling Ocean/Haigh Street Weighbridge and Sample Geraldton WA 2013 Co Operative Bulk Handling
Co Operative Bulk Handling Kalannie Wheat Silo Conveyor and Elevator Upgrade Kalannie WA 2013 Co Operative Bulk Handling
Mummaloo Mine Site Installation of Power Station Wubin WA 2014 Top Iron Pty Ltd
Roy Hill Mine Site Heavy Vehicle Yard  Newman WA 2014 Downer Mining EDI
Mummaloo Mine Site Process Plant Wubin WA 2014 Top Iron Pty Ltd
Wodgina Mine Site Power Line Installation and Infrastructure Upgrade Pilbara WA 2014 Global Advanced Metals
Co Operative Bulk Handling Install 2 Conveyor Loader Systems Moonyoonooka WA  2014 Co Operative Bulk Handling
Co Operative Bulk Handling Upgrade 4 Augers Canna WA 2014 Co Operative Bulk Handling
Eastlyn Estate Stage 7 URD installation to 26 x 2000m2 residential blocks Geraldton WA 2014 GPC Earthmoving
Seafields Estate Stage 2A URD installation to sub-division Geraldton WA 2014 CLW Earthmoving
Qube Storage Shed Electrical Design/Construction of Storage Sheds Narngulu WA 2014-2015 Q Design & Construct
Western Turner Syncline S10 Link Road and 33kv Underground Powerline Works Tom Price WA 2014-2015 Brierty
Geraldton Port Berth 6 Lighting Upgrade Geraldton WA 2015 Midwest Ports
Yungngora Power Station 200kW Solar Farm

Fitzroy Crossing, WA

2015  MPower
Geraldton Port Decommissioning of cathodic protection at Berths 3, 4, 5 and 6.

Geraldton WA

2015 Midwest Ports
CiticPacific Sino Iron Project Provide Labour Hire - Intelligent Lubrication System Installation – Concentrator Lines 3-6 Contract

Cape Preston, WA

2015 Karridale Group Pty Ltd
Thunderbox Gold Mine Electrical & instrumentation works on the Gravity Control Circuit

Leinster, WA

2016 Interquip
Midwest Port Authority Midwest Port Authority CV03 and CV04 Conveyor Gallery Upgrade. 

Geraldton, WA

2016 Marine & Civil